A week ago Saturday I started the ductwork project. Pierre Gomes and Dan Keefe came over to help. Before they did, I managed to drain the boiler so I could re-run some the hot water supply to the baseboard heat. There was a 2″ main supply that ran along the beam where I wanted the ductwork to run – so it was right in the way. There were a couple of other lines that were also in the way, so the three of us ripped it down. It took the whole morning to disassemble the parts that I needed to re-use. Once we did, we ran PEX to replace what we ripped out. That’s all of the white pipe you see in the pictures. The PEX was super-simple to run and there haven’t been any leaks in it yet.

Pierre had to leave to work on his own kitchen that afternoon, so Dan and I began putting together 5″ rounds for the supply runs to each of the first floor rooms. On the first floor, there are 7 5″ supplies and 2 6″ supplies as well as a split 6″ supply to the kitchen, which I have yet to be run.

On Sunday, Stephanie and the boys helped out with some insulating of the rounds. We did get some main trunk put together as well.

I also took off Tuesday and Thursday because the driller was originally supposed to show up Tuesday, but ended up re-scheduling for Thursday. So, on Tuesday, I got most of the vent holes cut on the first floor. I also had 4 of the 7 5″ supplies connected up to the register boots. I wanted to get that out of the way so that life could go on as usual on the first floor.

On Thursday, they also delivered the WaterFurnace unit. I ended up spending most of the morning sorting things out with the driller, George, and the Achieve delivery guys, Rob and Ryan. We dug up the septic system d-box (distribution box) because the wells have to be at least 25′ away from any septic components. That took some time because the plan o the title 5 was not very complete and in fact was off by several feet on the d-box location. I called the guy up to find out about septic field dimensions, and he tells me that the as-built plans on file at the town hall has that. I call up the town and there are no as-built plans on file. The board of health lady was sympathetic. It appears the inspector just made it up when he checked off the reference to as-built plans on the title 5. Looks like lazy work to me, but Stephanie like the term forgery.

There are a few pictures of the delivery guys bringing the unit into the basement. It weighs a lot. For the rest of the afternoon, I ran the other half of the 1st floor supply lines, 2 6″ lines, 1 5″, and two vent holes for 5″ lines in the school room. The two I didn’t run lines for are short runs that I will run after the supply plenum is in place.

Thursday afternoon, George the driller called back. He spoke with the town board of health and conservation commission. Apparently I’m the first and only homeowner in Easton who’s installing a geothermal system. The board of health guy, Rob, was very excited about the project and wanted to be there for the drill as much as I do. He also wanted to look at the d-box personally to ensure that it does what the title 5 says it does. The conservation commission also wants to look at the site since we’re on the outer edge of conservation land. In Easton, that is pretty much every house in town since there is so much of it everywhere. There are a couple of acres that sit in the middle of the block that our house sits on. And we have a bit of a pond that is half on our lot and half on the conservation land – our back yard.

Thursday evening, I wrote up a list of a couple more things I needed for duct components and sent that off to my hvac supplier, ControlAir Systems in Revere. Al Lavargna, the VP, is great (they’re expensive, but worth every penny) – he called be back in the morning, asked if I was working on this over the weekend (I said yes, of course), and he had his guys make the components that day and delivered them that afternoon (Friday).

That brings me to this past weekend. Pierre came over again for the morning and together, we got the supply plenum up into position. He also made a good dent in the cutout under the bathroom vanity for a supply into the 1st floor bathroom. I spent the day working on the larger half of the 1st floor supply trunk. We lined it up, took measurements for the holes to the supply runs, and insulated it. After he left, I was able to get that part connected and fastened to the joists.

On Sunday, I worked on the 2nd half of the 1st floor supply trunk. Since it was so long (almost the full width of the house and about 30′ of trunk), I had to break it into 2 halves. I also need to do that so I could get the pieces up and over the PEX tubing we ran last weekend. Using rope and a lot of cursing, I was able to hoist the second half up and into place last night. The hard part of this one was the top take-offs for the supply runs. There are hot and cold water supply lines that are on this half of the basement and they are in the way of everything. I really didn’t want to re-run the whole house’s plumbing, so I worked around them. There is just enough space to put some of the take-offs in, but I had to use starter-collars and elbows for a couple of spots since the take-offs are too long to fit between the pipes. The elbows, when straight and vertical, do fit. once they’re up, they can be turned and twisted into an elbow.

I also spent some time going through all of the duct that Al delivered two Thursdays ago. I think there are quite a few extra pieces of trunk and some things I can’t figure out what they are for. Kind of like those some-assembly-required projects with a few extra nuts and bolts that don’t seem to have a home. Except these nuts and bolts are 4′ tall 12″x16″ trunk segments.

This week, I’m avidly awaiting word on when the driller will be back out. I so want to be there for the drill.